The Community Infrastructure Levy's charges become due from the commencement date of a chargeable development.

When planning permission is granted, the council will issue a liability notice setting out the amount of the levy and the payment procedure. Once a commencement notice has been received, the council will issue a demand notice. This will detail who is liable for payment and confirm the amount payable, as well as any reliefs or surcharges. It will also specify the date and instalments on which payments are due.

Where the instalment policy does not apply, the chargeable amount must be paid in full within 60 days of the notified or deemed commencement date of the chargeable development.

Please read the Instalments and Exemptions Policy within the charging schedule for details of when payment in instalments is allowed what timescales are applicable.

Last updated on 05/11/2018