If you wish to demolish a building or structure you must notify the Council 6 weeks before you intend work to start by completing a Notice of Demolition. Once this has been received the Council is then responsible for identifying action required and providing a formal response under Sections 81 & 82 of the Building Act 1984. The target response time is 5 working days.
Stratford District Council's Demolitions Policy is available to download.
For further information please contact the Building Control Team on 01789 260626, by emailing buildingcontrol@stratford-dc.gov.uk or by fax on 01789 260630.